NEW DELHI — Tata Motors is racing to produce several thousand units of the inexpensive Nano in the next few months, say three suppliers and a Tata operations executive.

Because of plant-construction problems, the cars are being built on temporary lines at Tata plants — a move that will increase costs but avoid a long delay in the Nano introduction. The Nano, powered by a two-cylinder engine, has gained global interest because Tata expects to sell it to dealers for about $2,500.

Tata was scheduled to start production at a plant in Singur, on India’s east coast, in the fourth quarter and build 100,000 in the first 12 months. But it was forced to relocate its $350 million investment in production lines and equipment from Singur after nearly 45,000 protesters ringed the site in August. Farmers and others protested confiscation of land for the plant.

The controversy resulted in Tata Motors missing its launch goal. “It has become a matter of priority for there to be at least some Nanos available for sale as soon as possible,” said the operations executive, who asked not to be named because he was revealing information he was not authorized to share. “For those first few thousand vehicles, it’s very difficult to keep prices down, because the production lines will be temporary.”

Suppliers say Tata is adding production lines to plants in Pantnagar, where it normally builds light commercial vehicles, and in Pune, an automobile production hub.

Those plants may produce a combined total of about 5,000 vehicles a month, said another supplier. He based his estimate on the number of parts his New Delhi company has been asked to deliver.

The added costs of transporting parts all around the country and creating temporary production lines might result in lowered profits or even losses on the margins of the car. The original plan called for suppliers set up within 0.62 miles of the production site to keep transport costs down.

Meanwhile, Tata has taken possession of land in Sanand, in Gujarat state, for a new permanent factory for the Nano. But “that plant is far from ready,” said a supplier, who declined to be named.

Tata did not confirm the production plans at the temporary sites. The company said: “While awaiting the Sanand plant’s completion, Tata Motors will explore the possibility of manufacturing the Nano at its existing facilities at Pune and Pantnagar, and launch the car in the January-March quarter.” 

[Source: Automotive News Europe]

 

 

Clive Goldthorp

About the Author:

Clive claims that his interest in the BMC>MG story dates back to his childhood in the 1960s when the family’s garage premises were leased to a tenant with an Austin agency. However, back in the 1920s and 1930s, his grandmother was one of the country’s first female Garage Proprietors so cars probably run in his genes! Admits to affairs with Alfa Romeos, but has more recently owned an 06/06 MG TF 135 and then a 15/64 MG3 Style… Clive, who was AROnline’s News Editor for nearly four years, stood down from that role in order to devote more time to various Motor Racing projects but still contributes articles on as regular basis as his other commitments permit.